Pictures show work in progress when brick work reached lintel level
Flat sunshades,lintel and loft slabs will be concreted now followed by slope sunshades and slope roof for car porch and sit out.
Round columns will also be concreted to reach 220 level before slope roof for car porch and slope sunshades come in.
2600 sft four bed room two storeyed house at Punthala near Chengannur for Mr.Zachariah John living and working at Kingdom of Saudi Arabia
Friday, September 25, 2009
Wednesday, September 16, 2009
Tuesday, September 8, 2009
Brick work commencement
Brick work commenced and door window frames arrived at site except few windows.Pictures show work commencement.First layer of brick were fixed for the brick work.Openings starting from floor level were marked